Home / CERTIFICATE OF COMPLETION AND COMPLIANCE/PRINCIPAL SUBMITTING PERSON (PSP)/ This Question

WHAT HAPPENS IF THE FORM IS NOT APPLICABLE

Last Updated: 11 Oct 2021 12:30 PM

STEP 1

Page: Home Page

    1. Please navigate to Certificate of Completion & Compliance (CCC) on the left panel

    2. Click on "My CCC List"


STEP 2

Page: Certificate of Completion & Compliance (CCC)

    Please click on the project title on the selected CCC


STEP 3

Page: CCC Form Overview

    Please select the forms and click on "Update"


STEP 4

Page CCC Form

The form will be divided into 4 sections

Sections 1

    Please move the slider to X


Section 2

    Please accept the declaration


STEP 5 - Update 1st Time

    Please click on "Update" to save the entry


STEP 6

1. After updating, PSP would have to download the form D/G under "Action" button

2. PSP would need to sign and stamp the print copy of Form D/G


STEP 7

1. Once Form D/G is ready (Signed and stamped), PSP are required to upload the Form


STEP 8 - Update 2nd/Final Time

1. PSP has to click on "Update" again for the final time

2. Once confirmed, the process is irreversible. For any changes, please contact BEM

3. System will email PSP to notify regarding the submission.


INFORMATION

A

Form G11 is not completed as the form was

- Verified

- Form was not uploaded


B

Form G11 is completed as the form was

- Verified